All projects

PECL-2618 · LIC 0409876

Simonette 2-7 Risk Screen

Simonette · Regional travel · Sour service standby, muskeg edge

Class 3
Reporting

Actual spend

$398.7K

97% of $412K

Budget variance

-$13.3K

-3.2% vs budget

Drilling cost per metre

$612

Cost per productive hour

$244

+3.4% vs Class 3 median

Metres per productive hour

1.09

232 m over 212 hrs

Analytical spend

$88.2K

158 samples · 31% rush

Consulting spend

$58.5K

346 hours logged

Non-productive time

21%

56 of 268 hrs

Project cost composition

Actual spend by cost class for this project.

Field and context metrics

Boreholes
16
Total metres
232 m
Monitoring wells
7
Productive hours
212
Non-productive hours
56
Average depth
14.5 m
Drilling method
Sonic
Travel classification
Regional
Complexity class
Class 3
Project lead
Burton Reid

Budget against actual

By cost category, so the cause of variance is immediately obvious.

Efficiency against benchmark

Compared with the Class 3 illustrative range.

Illustrative benchmark
Cost / productive hour
$244
Class 3 illustrative median
$236
Expected range
$208 - $268
Difference
+3.4% vs median

Cobble/refusal risk, well installs, muskeg matting

Budget consumed

$398,700 of $412,000

Vertical concentration profile

F3 concentration against Tier 1 criteria, mg/kg.

Borehole depth profile

Completed boreholes by depth interval.

  • 0-3 m26
  • 3-6 m34
  • 6-9 m21
  • 9-12 m12
  • 12 m +5

Analytical requests

eCOC submissions raised against this project.

RequestLaboratorySamplesTurnaroundEstimateStatus
eCOC-4804Element - Grande Prairie34Rush 3-day$22,410Flagged

Decision status

Risk-based

Confidence: Medium · Risk 64/100

-62.0% cost upside

Exceedance driven by an excludable irrigation pathway

  • Hydrocarbons1.30×Exceed
  • Metals0.28×Pass
  • PAHs0.91×Review
  • Salinity0.54×Pass
Vertical
Closed at 5.0 m
Lateral
Delineated on all boundaries
Exposure
$690K