Metrics Dashboard

Assessment efficiency

Every unit rate is normalized for complexity class, travel band and ground conditions, so comparisons across sites are defensible.

Cost per productive hour

$215

+4.3% vs FY25

Cost per metre

$268

-3.1% vs FY25

Cost per monitoring well

$18,940

+1.7% vs FY25

Non-productive time

21.9%

-6.2% vs FY2558,182 productive hrs

Rate versus depth advanced

Bubble size is borehole count. Sites above the band warrant scope review.

Class 1 Class 2 Class 3 Class 4

Complexity benchmarks

Expected $/hr band by class.

Travel bands

Mobilisation distance drives both rate and lost time.

  • Local$178/hr

    21,480 hrs logged · 9% non-productive

  • Regional$225/hr

    24,140 hrs logged · 18% non-productive

  • Remote$309/hr

    12,562 hrs logged · 31% non-productive

Borehole depth profile

Distribution of completed boreholes.

  • 0-3 m26
  • 3-6 m34
  • 6-9 m21
  • 9-12 m12
  • 12 m +5

Benchmark definitions

What each class assumes.

  • Class 1
    $148-$186/hr

    Access-ready, single pad, augerable overburden

  • Class 2
    $176-$224/hr

    Winter access, mixed till, 2-4 boreholes

  • Class 3
    $208-$268/hr

    Cobble/refusal risk, well installs, muskeg matting

  • Class 4
    $252-$344/hr

    Remote fly/barge, sour service, deep delineation

Project-level unit economics

Compare each project against its class band.

ProjectClassTravelMetres$/hrBand medianvs bandNPT

Fox Creek 14-22 PSI

Cobble refusal at 6.5 m on 4 locations

Class 3
Regional214$258$236+9.5% 25%

Kaybob South 3-11 DSA

Dry till, unrestricted access

Class 2
Local156$193$198-2.7% 15%

Chinchaga 8-30 Delineation

Matting required, 140 km winter haul

Class 4
Remote402$306$292+4.9% 27%

Wapiti 6-19 Reclamation Cert

Cultivated quarter, summer access

Class 1
Local62$162$165-1.9% 13%

Gold Creek 11-4 PSI

Shallow groundwater, sloughing sidewalls

Class 2
Regional148$209$198+5.5% 19%

Simonette 2-7 Risk Screen

Sour service standby, muskeg edge

Class 3
Regional232$244$236+3.4% 21%