Metrics Dashboard
Assessment efficiency
Every unit rate is normalized for complexity class, travel band and ground conditions, so comparisons across sites are defensible.
Cost per productive hour
$215
Cost per metre
$268
Cost per monitoring well
$18,940
Non-productive time
21.9%
Rate versus depth advanced
Bubble size is borehole count. Sites above the band warrant scope review.
Complexity benchmarks
Expected $/hr band by class.
Travel bands
Mobilisation distance drives both rate and lost time.
- Local$178/hr
21,480 hrs logged · 9% non-productive
- Regional$225/hr
24,140 hrs logged · 18% non-productive
- Remote$309/hr
12,562 hrs logged · 31% non-productive
Borehole depth profile
Distribution of completed boreholes.
- 0-3 m26
- 3-6 m34
- 6-9 m21
- 9-12 m12
- 12 m +5
Benchmark definitions
What each class assumes.
- Class 1$148-$186/hr
Access-ready, single pad, augerable overburden
- Class 2$176-$224/hr
Winter access, mixed till, 2-4 boreholes
- Class 3$208-$268/hr
Cobble/refusal risk, well installs, muskeg matting
- Class 4$252-$344/hr
Remote fly/barge, sour service, deep delineation
Project-level unit economics
Compare each project against its class band.
| Project | Class | Travel | Metres | $/hr | Band median | vs band | NPT |
|---|---|---|---|---|---|---|---|
Fox Creek 14-22 PSI Cobble refusal at 6.5 m on 4 locations | Class 3 | Regional | 214 | $258 | $236 | +9.5% | 25% |
Kaybob South 3-11 DSA Dry till, unrestricted access | Class 2 | Local | 156 | $193 | $198 | -2.7% | 15% |
Chinchaga 8-30 Delineation Matting required, 140 km winter haul | Class 4 | Remote | 402 | $306 | $292 | +4.9% | 27% |
Wapiti 6-19 Reclamation Cert Cultivated quarter, summer access | Class 1 | Local | 62 | $162 | $165 | -1.9% | 13% |
Gold Creek 11-4 PSI Shallow groundwater, sloughing sidewalls | Class 2 | Regional | 148 | $209 | $198 | +5.5% | 19% |
Simonette 2-7 Risk Screen Sour service standby, muskeg edge | Class 3 | Regional | 232 | $244 | $236 | +3.4% | 21% |