Metrics Dashboard

Analytical scope

Are we testing what we planned to test, and what is driving laboratory cost?

Rush target < 10%

Analytical spend

$2.3M

of $2M budget

Analytical budget variance

$244K

+12.0% vs budget

Samples submitted

1,898

1,830 planned in SOW

Rush / premium spend

$268.4K

4.7% of analytical spend

Out-of-package add-on spend

$44K

82 samples

Scope adherence

96.4%

Planned versus actual analytical scope

Approved SOW scope beside what was actually submitted, by project.

Spend by analyte group

Laboratory spend per configured package.

Turnaround mix

Regular versus rush samples by project, so premium spend is traceable.

Analytical spend trend

Actual against budget over time, thousands CAD.

Projects driving analytical variance

Planned against actual scope, with the premium and add-on spend behind each variance.

ProjectPlanned samplesActual samplesBudgetActual spendRush spendAdd-on spendVariance
Chinchaga 8-30 Delineation210262$138K$168.9K$41.2K$18.4K+22.4%
Fox Creek 14-22 PSI130148$82K$96.4K$28.4K$9.6K+17.6%
Gold Creek 11-4 PSI98112$54K$61.3K$8.9K$4.2K+13.5%
Simonette 2-7 Risk Screen132158$78K$88.2K$24.6K$11.8K+13.1%
Kaybob South 3-11 DSA10496$56K$52.1K$3.2K--7.0%
Wapiti 6-19 Reclamation Cert4844$21K$18.6K---11.4%

Out-of-package add-ons

Additional analyses outside the approved package, and why they were requested.

ProjectAdd-on samplesAdd-on spendPrimary reasonScope status
Fox Creek 14-22 PSI18$9.6KPAHs added on observed sheenWatch
Chinchaga 8-30 Delineation34$18.4KStep-out salinity beyond approved gridInvestigate
Gold Creek 11-4 PSI8$4.2KDissolved metals added at MW-02Watch
Simonette 2-7 Risk Screen22$11.8KPAH confirmation for risk pathwayInvestigate