PECL-2612 · LIC 0367440
Wapiti 6-19 Reclamation Cert
Wapiti · Local travel · Cultivated quarter, summer access
Actual spend
$148.9K
Budget variance
-$23.1K
Drilling cost per metre
$839
Cost per productive hour
$162
Metres per productive hour
0.67
Analytical spend
$18.6K
Consulting spend
$34.3K
Non-productive time
13%
Project cost composition
Actual spend by cost class for this project.
Field and context metrics
- Boreholes
- 8
- Total metres
- 62 m
- Monitoring wells
- 0
- Productive hours
- 92
- Non-productive hours
- 14
- Average depth
- 7.8 m
- Drilling method
- Hand auger / test pit
- Travel classification
- Local
- Complexity class
- Class 1
- Project lead
- Valerie Osei
Budget against actual
By cost category, so the cause of variance is immediately obvious.
Efficiency against benchmark
Compared with the Class 1 illustrative range.
- Cost / productive hour
- $162
- Class 1 illustrative median
- $165
- Expected range
- $148 - $186
- Difference
- -1.9% vs median
Access-ready, single pad, augerable overburden
Budget consumed
$148,900 of $172,000
Vertical concentration profile
F3 concentration against Tier 1 criteria, mg/kg.
Borehole depth profile
Completed boreholes by depth interval.
- 0-3 m26
- 3-6 m34
- 6-9 m21
- 9-12 m12
- 12 m +5
Analytical requests
eCOC submissions raised against this project.
No analytical requests raised for this project.
Decision status
Closure ready
Confidence: High · Risk 12/100
All analyte groups below Tier 1 criteria
- Hydrocarbons0.21×Pass
- Metals0.14×Pass
- PAHs0.11×Pass
- Salinity0.38×Pass
- Vertical
- Closed at 3.0 m
- Lateral
- Delineated
- Exposure
- $0