PECL-2609 · LIC 0455102

Chinchaga 8-30 Delineation

Chinchaga · Remote travel · Matting required, 140 km winter haul

Class 4
Field

Actual spend

$742.5K

108% of $690K

Budget variance

$52.5K

+7.6% vs budget

Drilling cost per metre

$667

Cost per productive hour

$306

+4.9% vs Class 4 median

Metres per productive hour

1.16

402 m over 348 hrs

Analytical spend

$168.9K

262 samples · 24% rush

Consulting spend

$92.6K

512 hours logged

Non-productive time

27%

128 of 476 hrs

Project cost composition

Actual spend by cost class for this project.

Field and context metrics

Boreholes
26
Total metres
402 m
Monitoring wells
9
Productive hours
348
Non-productive hours
128
Average depth
15.5 m
Drilling method
Sonic
Travel classification
Remote
Complexity class
Class 4
Project lead
Jake Morrow

Budget against actual

By cost category, so the cause of variance is immediately obvious.

Efficiency against benchmark

Compared with the Class 4 illustrative range.

Illustrative benchmark
Cost / productive hour
$306
Class 4 illustrative median
$292
Expected range
$252 - $344
Difference
+4.9% vs median

Remote fly/barge, sour service, deep delineation

Budget consumed

$742,500 of $690,000

Vertical concentration profile

F3 concentration against Tier 1 criteria, mg/kg.

Borehole depth profile

Completed boreholes by depth interval.

  • 0-3 m26
  • 3-6 m34
  • 6-9 m21
  • 9-12 m12
  • 12 m +5

Analytical requests

eCOC submissions raised against this project.

RequestLaboratorySamplesTurnaroundEstimateStatus
eCOC-4821Bureau Veritas - Edmonton42Rush 3-day$28,640Awaiting review

Decision status

Delineate

Confidence: Medium · Risk 78/100

-51.0% cost upside

Salinity plume open laterally, vertical closure unproven

  • Hydrocarbons0.88×Review
  • Metals0.31×Pass
  • PAHs0.22×Pass
  • Salinity2.60×Exceed
Vertical
Unproven below 9 m
Lateral
Open on 3 of 4 boundaries
Exposure
$2.7M