PECL-2604 · LIC 0398211
Kaybob South 3-11 DSA
Kaybob · Local travel · Dry till, unrestricted access
Class 2
LabSpend to date
$312.8K
-10.1% vs budget90% of $348K
Rate per productive hour
$193
-2.7% vs Class 2 median
Non-productive time
15%
32 of 210 hrs
Analytical spend
$52.1K
96 samples · 8% rush
Cost composition
Actual against budget by cost class for this project.
Field summary
- Boreholes
- 12
- Metres advanced
- 156 m
- Monitoring wells
- 4
- Productive hours
- 178
- Standby / NPT hours
- 32
- Cost per metre
- $2,005
- Project lead
- Burton Reid
Budget utilisation
$312,800 of $348,000
Depth profile
F3 concentration against Tier 1 criteria, mg/kg.
Borehole distribution
Completed boreholes by depth interval.
- 0-3 m26
- 3-6 m34
- 6-9 m21
- 9-12 m12
- 12 m +5